, , ,

MSC Baltic III Wreck Removal Reaches 63 Percent

With 63% of vessel tonnage removed, MSC Baltic III’s dismantling still involves shoreward pulls, residual fuel and shoreline work.

By Ships Archive

·

MSC Baltic III aground beside steep cliffs, with its bow name, three deck cranes and aft superstructure visible.

MSC Baltic III beside the cliffs near Lark Harbour, Newfoundland and Labrador, on July 28, 2025, after its grounding. IMR2000 / Wikimedia Commons, CC0 1.0.

By 9 October 2026 salvors had removed 6,964 tonnes of MSC Baltic III from Cedar Cove in western Newfoundland, about 63 percent of the vessel’s tonnage, according to the Canadian Coast Guard. Resolve Marine has pulled the bow and midship sections 137 metres towards shore and the stern 25 metres. Rough seas that week brought renewed sheening and oiled vegetation along the shoreline.

FactDetail
VesselMSC Baltic III
Grounding15 February 2025
LocationCedar Cove, western Newfoundland
Crew rescuedAll 20
Removal contractorResolve Marine
Latest tally6,964 tonnes; about 63%
Status date9 October 2026

The grounding

The container ship Nordbaltic, later MSC Baltic III, afloat at Casablanca with containers and three deck cranes.
MSC Baltic III under its former name Nordbaltic, Casablanca, Morocco, 2018. Photo: Farid mernissi, Wikimedia Commons, CC BY-SA 4.0. Resized and compressed.

The casualty began on 15 February 2025 when MSC Baltic III lost power and grounded outside the entrance to the Bay of Islands, Newfoundland and Labrador. A Fisheries and Oceans Canada briefing records the Canadian Armed Forces’ airlift of all 20 crew members.

Instead of refloating her, Resolve is pulling damaged sections towards a shore work area and cutting them up there.

Coast Guard entries for December 2025 and January 2026 record further buckling and cracking after severe weather.

Roads, cableway and scrap pad

Much of the work preceding the current tonnage milestone concerned access. The Coast Guard’s June and July entries describe improvements to the Cedar Cove road, work on a switchback route to the beach, cargo removal and preparations for equipment to handle contaminated water.

Earlier in the response, a cableway connected shore and wreck. By the 9 September update, that system was being dismantled, with workers using a temporary gangway. The same entry records completion of a shoreline scrap pad supporting a crane for lightering operations.

The July log also separates cargo handling from hull dismantling. It records progressive removal of containers, while the 6 August entry states that cargo removal and superstructure deconstruction were complete.

Pulling her ashore

Pulling began on 31 July 2026, according to the Coast Guard’s 6 August notice. That entry described gradual shoreward movement followed by deconstruction as the wreck came ashore. The 9 September report added that further pulls were planned for high tides to obtain additional buoyancy.

The 2 October update records a 42-metre pull on 27 September that made the bow and midship sections accessible from the scrap pad. The next update reports a further 31 metres, bringing their cumulative movement to 137 metres. The stern had meanwhile entered its own pulling phase.

Tonnage removed

The Coast Guard reported approximately 6,086 tonnes removed on 2 October, or close to 55% of total vessel tonnage. On 9 October the tally was 6,964 tonnes, approximately 63%. Subtracting the published totals gives an increase of 878 tonnes between the two reporting snapshots.

The figure counts tonnes of wreck removed; it is not gross tonnage or a measure of overall progress.

Oil on the shore

The latest notice reports sheening in Cedar Cove and shoreline impacts involving oiled vegetation and debris following rough seas. It states that residual fuel remains aboard, that accessible tanks continue to be cleaned and that on-water containment and recovery have increased as conditions permit.

Weather influences both the problem and the response. The Coast Guard says aerial and on-water monitoring depends on the weather.

What comes next

The Coast Guard’s May entry identifies its role as reviewing the owner’s proposed removal plan for public safety and environmental protection, with Resolve retained as contractor.

No completion date has been published. Pulling of the stern, cutting and shoreline cleaning were all continuing in October.

Sources and further reading

Related reading: MSC Napoli: Structural Failure in the Channel and the Beaching at Branscombe · Rena on Astrolabe Reef: The 2011 Grounding and Its Aftermath